Revised September 2009
|
Architect |
McMillan Smith & Partners Architects, PLLC |
|
|
Location |
Site of Existing DHS |
|
|
Address |
1819 Six Mile Highway, Central, SC 29630 |
|
|
Acreage |
92.78 Acres |
64.7 – Existing Site |
|
4.42 – New Purchase |
||
|
23.66 – New Purchase |
||
|
September 2009 Board Action: The school will be built on the 64.7 acres of the existing site. |
||
|
Cost of Property |
$1,641,856 |
|
|
Core Size |
1343 (1033 Students + 30% Growth Factor) |
|
|
Square Footage |
226,820 |
|
|
Site/Construction Package Expected Out for Bid |
February 2010 |
|
|
Builder |
Trehel/Balfour Beatty Construction |
|
|
Scheduled Construction Time |
26 months |
|
|
Expected Occupancy Date |
August 2012 |
|
|
* Schools will be built with administration and guidance areas, cafeterias and kitchens, media centers, gymnasiums, locker rooms, auditoriums and fine arts facilities to handle the 2007-2008 45-day enrollment and the approved growth factor. The designs allow for constructing more classrooms if the projected growth occurs. |
||
|
Updated September 17, 2009 |
||